Schneider Electric is doubling production capacity for liquid cooling units at its site in Conselve. Chiller production and test capacity are also going up, to meet demand from AI and data centres in Europe.
Schneider Electric is expanding its European production of cooling systems in Conselve, in the Italian region of Veneto. It is the company’s largest European production site for cooling and a centre for research and development, engineering and technical training. The expansion follows the acquisition of Motivair last year. According to Schneider Electric, it brings engineering and technical expertise closer to customers in Europe.
More capacity for CDUs and chillers
From January 2027, Schneider Electric will increase production capacity for Cooling Distribution Units (CDUs) by 100 percent. Production of large chillers will rise by 50 percent by the end of 2026.
The company points to AI workloads, which bring higher power densities per rack and stricter requirements for heat removal. According to Schneider Electric, this makes liquid cooling essential for the next generation of data centres.
The workforce in Conselve has almost doubled over the past five years, with growth in engineering, production, quality assurance and technical roles.
New test laboratory
Schneider Electric is also building a cooling test laboratory. It is due to be ready in December 2027 and will triple current test capacity. The lab will be used for research and development, product validation and quality assurance of air and liquid cooling. Chillers can be tested there up to 4 MW, CDUs from Motivair by Schneider Electric up to 5 MW, and CRAH units and fanwall systems up to 800 kW.
Damien Dhellemmes, senior vice president Secure Power and Data Center Business in Europe at Schneider Electric, explains the demand for AI infrastructure: “AI is fundamentally changing the way our customers design and manage data centres. This is creating strong demand for liquid cooling that can support increasingly powerful computing systems.”
The higher chiller production comes first, by the end of 2026. The doubled CDU capacity will be available from January 2027, and the test laboratory will follow in December 2027.