The Walloon Region is halting construction of the Google data centre in Farciennes. The permit for Google’s amended plans has no longer been valid since the summer.
The Walloon Region is halting construction of Google’s data centre complex in Farciennes, near Charleroi, reports VRT NWS. The amended permit has no longer been valid since August. According to Greenpeace, Google kept building in the meantime.
Google is building through its European subsidiary Crystal Computing on the Ecopôle, a business park spread across Farciennes, Aiseau-Presles and Sambreville. Google’s site covers 53 hectares, the equivalent of 74 football pitches. The company bought the land in 2021 and announced an additional investment of one billion euros when construction started, as we reported earlier on ITdaily.
Amended permit for data centre in Farciennes
In 2024, Google received a permit for three smaller data centres. In 2025, the company asked to merge two of them into one much larger building and to replace the planned air cooling with water cooling using water from the Sambre, reports RTBF. The Walloon administration approved that amendment in April. A month later, a citizens’ appeal followed.
In August, François Desquesnes (Les Engagés), the Walloon minister responsible for spatial planning and infrastructure, among other things, opposed the amendment. He pointed to the data centre’s water needs. Google took the matter to the Council of State.
Greenpeace demands a halt
Based on satellite images, Greenpeace claims that the work simply continued. On Wednesday 25 November, the organisation started an urgent procedure with the Walloon administration to have the site halted immediately, RTBF learned.
Desquesnes’s cabinet says the original 2024 permit remains valid. Google may build under that permit, but not under the amended plans. Regional officials are checking whether the ongoing work complies with the rules. If they find violations, an official report will follow and go to the public prosecutor’s office.
Greenpeace links the project to Google’s water consumption in Saint-Ghislain, near Mons. According to the organisation, a comparable data centre there pumps up one billion litres of water a year to cool data centres, of which only a quarter is returned. Google Belgium has not yet responded to questions from RTBF.
Hearing on 7 January
The Council of State will consider Google’s appeal against the minister’s decision on 7 January. In the meantime, the Region’s inspections and Greenpeace’s urgent procedure are also still ongoing.